Sunday, September 16, 2007

Assignment 1 / Task 7 / ITC493

Task 7: (Chapter 6, Exercise 1)

Using Figure 6-2, enter the activities, their durations, and their relationships in Project 2003. Use a project start date of June 1, 2005. View the network diagram. Does it look like Figure 6-4? Print the network diagram on one page. Return to Gantt Chart view. Click View on the menu bar, select Table: Entry, and then click Schedule to recreate Table 6-1. You may need to move the split bar to the right to reveal all of the table columns. Write a few paragraphs explaining what the network diagram and schedule table show concerning Project X's schedule.






From the above diagram we can say that due to dependencies Task E and F can not start until task B is completed. Task D can not start until task A is completed. Task H can not start until Task D and E completed. Task J can not start until Task F, H, and I completed.